Air Source Heat Pump Install – Dichling

CASE STUDY

Case Study - Dichling

Unusual aspect:

This project presented several unique challenges that required a bespoke approach:

  • A custom metal frame was designed and fabricated to support the heat pump unit. This allowed the unit to be elevated sufficiently to ensure clear airflow for efficient operation.
  • The property’s flint walls prevented standard wall mounting, meaning the system had to be fully self-supporting rather than fixed directly to the structure.
  • Internally, the building featured timber-framed vaulted ceilings, which required careful planning around pipe routing and installation access.
  • The heating system was designed to work with underfloor heating throughout the property, influencing system design, flow temperatures, and overall layout.

Challenges:

 

  • The property had restricted access due to scaffolding which limited access to installation areas. Careful coordination with other trades was required to safely transport and position equipment, particularly the external heat pump unit.
  • The new build has a large footprint with multiple rooms, this required longer pipe runs, careful zoning for underfloor heating and strategic placement of manifolds.
  • As this is a new build installation, works had to be timed alongside, structural works and first and second fix stages so coordination was critical to avoid delays and rework.

Project Key Facts

Design flow temperature – 40 Celsius

Total heat loss – 10349.93 W

SCOP rating – 5.20

Grant Aerona3 10KW R32 Air Source Heat Pump

Grant quick recovery 210L pre plumbed, single coil hot water cylinder with smart controls

New Build Installation

Project Images

See how our Sustainable

heating solutions can benefit your projects

No matter what stage of a project you are at, we would love to speak with you and find out more about your needs and how we can help.


Contact us today below

More Case Studies

Scroll to Top